Concrete Calculator

Use this concrete calculator to estimate the amount of concrete needed for slabs, driveways, footings, patios, foundations and sidewalks using standard US measurements.

By ConstructlyTools Editorial Team · Published: January 15, 2026 · Updated: April 11, 2026 · Sources: ACI 318 · RSMeans · HomeAdvisor
Concrete Calculator
📐 Formula Used
Volume (cu ft) = Length × Width × (Thickness ÷ 12) · Cubic Yards = Volume ÷ 27 · Order Amount = Cu Yd × 1.10 (10% waste) · Sources: ACI 318, IRC
Concrete Needed
0 cu yd
Enter measurements above to get your estimate
Slab Area
0 sq ft
Volume (cu ft)
0 cu ft
Order (+ 10% waste)
0 cu yd
60 lb Bags Equiv.
0 bags

1 cu yd = 27 cu ft · 60 lb bag = ~0.45 cu ft · 80 lb bag = ~0.60 cu ft · Ready-mix sold by cu yd · Short-load fee applies for orders under 3–5 cu yd · Always specify air-entrained mix for exterior slabs in freeze-thaw climates

Always order 10% more than calculated. Confirm current pricing with your local ready-mix supplier before ordering.

Understanding the Calculator Inputs

This calculator converts your project dimensions into cubic yards — the unit ready-mix suppliers use to price and deliver concrete. Getting the inputs right before ordering is critical: running out mid-pour creates a cold joint, a serious structural defect that requires cutting out and re-pouring the affected section.

Length and Width

Measure the actual pour dimensions — the inside of your form boards, not the outside. For irregularly shaped slabs, break the area into rectangles, calculate each separately, and add the cubic yards together. For circular areas (like a round column pad): π × radius² × (thickness ÷ 12) ÷ 27.

Thickness — The Most Important Input

Thickness has a direct 1:1 effect on material volume and cost. A 6-inch slab uses exactly 50% more concrete than a 4-inch slab of the same area. Getting thickness right is the single most important step in concrete estimating. See the thickness guide below for the correct depth by application per ACI 318 and IRC standards.

Why 10% Waste Is Non-Negotiable

Concrete volume estimates assume a perfectly flat, perfectly dimensioned pour. Reality introduces: uneven subgrade (low spots hold more concrete), form boards that flex slightly under concrete weight, and small spillage at the truck chute. Running 5–10% short mid-pour means either stopping to order more — creating a cold joint at the stopping point — or accepting an incompletely filled form. Order the calculated result plus 10%, always.

💡 Under 1 Cu Yd? Use Bags. Over 1 Cu Yd? Use Ready-Mix.

The crossover point between bags and ready-mix is approximately 1 cubic yard. Under 1 yard, bags are more convenient despite higher cost per yard. Over 1 yard, ready-mix is dramatically cheaper — a cubic yard of ready-mix costs $125–$200 delivered vs $400–$500 in 60 lb bags for the same volume. The calculator shows both — use the bag figure to confirm when ready-mix makes sense.

3 Real-World Concrete Examples

Example 1 — Backyard Patio Slab (20×20 ft, 4 inches, DIY)

A standard residential patio slab. 4-inch thickness, compacted gravel base, rebar on 18-inch grid, DIY pour with rented screed and float.

Area:

20 × 20 = 400 sq ft

Volume:

400 × (4÷12) = 400 × 0.333 = 133.3 cu ft = 4.94 cu yd

Order amount (+ 10%):

4.94 × 1.10 = 5.43 → order 5.5 cu yd

ItemQtyUnit CostTotal
Ready-mix concrete (3,000 PSI, 5.5 cu yd)5.5 cu yd$130–$175/cu yd$715–$963
Compacted gravel base (4", 400 sq ft)~5 tons$35–$55/ton$175–$275
Rebar (#4, 18" grid, 400 sq ft)~300 LF$0.65–$0.90/LF$195–$270
Form lumber (2×4, 80 LF perimeter)80 LF$0.65–$1.00/LF$52–$80
Concrete screed + float rental1 day$60–$100$60–$100
Concrete sealer (after cure)2 gallons$25–$45/gal$50–$90
Total DIY materials + rental$1,247–$1,778
Contractor poured (same specs)$2,800–$4,800

Real-world note: A 5.5-yard pour is manageable as a DIY project but requires 4–5 helpers minimum — concrete exits the chute faster than most homeowners expect, and you have roughly 60–90 minutes of working time before it starts to stiffen. Rent a bull float and a 10-foot screed board. Have helpers positioned at the far end of the form before the truck arrives. Never add water at the chute — if the mix arrives too stiff, ask the driver to add a small amount of water only, and only before the pour starts.

Example 2 — Two-Car Garage Floor (24×24 ft, 6 inches, Contractor)

Standard 576 sq ft two-car garage slab. 6-inch thickness per code for vehicle traffic, 4,000 PSI air-entrained mix for freeze-thaw climate, rebar on 12-inch grid, vapor barrier under slab.

Area:

24 × 24 = 576 sq ft

Volume:

576 × (6÷12) = 576 × 0.5 = 288 cu ft = 10.67 cu yd

Order amount (+ 10%):

10.67 × 1.10 = 11.74 → order 12 cu yd

ItemQtyUnit CostTotal
Ready-mix (4,000 PSI, air-entrained, 12 cu yd)12 cu yd$145–$190/cu yd$1,740–$2,280
Compacted gravel base (4")~8 tons$35–$55/ton$280–$440
Vapor barrier (6 mil poly)576 sq ft$0.10–$0.20/sq ft$58–$115
Rebar (#4, 12" grid)~700 LF$0.65–$0.90/LF$455–$630
Labor (pour, screed, float, broom finish)576 sq ft$2–$4/sq ft$1,152–$2,304
Control joints (saw cut, 4 cuts)4 cuts × 24 ft$1–$2/LF$96–$192
Total contractor installed$3,781–$5,961

Real-world note: Garage slabs in freeze-thaw climates must use air-entrained concrete — tiny air bubbles in the mix that give freezing water room to expand without cracking the slab. Standard non-air-entrained mix will develop surface scaling within 3–5 winters if road salt or de-icer is tracked onto the surface. Always specify air entrainment when ordering in Zones 4–7. Ask your ready-mix supplier: “Is this mix air-entrained for exterior exposure?” before accepting the order.

Example 3 — Concrete Footings for a Deck (8 footings, 12-inch diameter × 42-inch deep)

Eight tube form footings for a 16×20 ft elevated deck. 12-inch diameter Sonotube forms, 42-inch depth below frost line in Zone 5, 3,000 PSI mix. Use our concrete footing calculator for exact volume.

Volume per footing (cylinder):

π × (0.5 ft)² × 3.5 ft = 3.14159 × 0.25 × 3.5 = 2.75 cu ft per footing

Total volume (8 footings):

8 × 2.75 = 22 cu ft = 0.81 cu yd

Order amount (+10%):

0.81 × 1.10 = 0.89 cu yd → use bags for this quantity

ItemQtyUnit CostTotal
80 lb concrete bags (0.60 cu ft each)40 bags$7–$10/bag$280–$400
12" Sonotube forms (42" length, 8 units)8 tubes$18–$28 each$144–$224
Rebar (#4, 2 per footing × 4 ft)64 LF$0.65–$0.90/LF$42–$58
Mixing tub or rented mixer1 day$50–$80$50–$80
Post base hardware (8 units)8$12–$20 each$96–$160
Total DIY footing materials$612–$922

Real-world note: At 0.81 cubic yards, bags make more sense than calling a ready-mix truck — minimum order fees alone would exceed the material cost. Mix each footing with 3–4 bags using a portable mixer. Set the post base hardware while the concrete is still wet — position precisely using a string line before the mix stiffens. Re-check alignment 10 minutes after setting.

Concrete Coverage Chart

Quick reference for common slab sizes and thicknesses. All figures are calculated volume — add 10% when ordering.

Slab SizeSq Ft4" thick5" thick6" thick8" thick
10×10 ft1001.2 cu yd1.5 cu yd1.9 cu yd2.5 cu yd
12×12 ft1441.8 cu yd2.2 cu yd2.7 cu yd3.6 cu yd
16×20 ft3203.9 cu yd4.9 cu yd5.9 cu yd7.9 cu yd
20×20 ft4004.9 cu yd6.2 cu yd7.4 cu yd9.9 cu yd
24×24 ft5767.1 cu yd8.9 cu yd10.7 cu yd14.2 cu yd
30×30 ft90011.1 cu yd13.9 cu yd16.7 cu yd22.2 cu yd
40×40 ft1,60019.8 cu yd24.7 cu yd29.6 cu yd39.5 cu yd

Calculated volume only. Add 10% to all figures when placing the order.

Thickness Guide by Application

Using the wrong thickness is one of the most expensive concrete mistakes. Here are the correct depths per application per ACI 318 and IRC standards.

ApplicationMin ThicknessRecommendedNotes
Sidewalks / walkways3 in4 in4" is code minimum in most jurisdictions
Residential patio3.5 in4 in4" standard; 5" for heavy outdoor furniture / hot tub
Residential driveway4 in5–6 in6" for trucks, RVs, heavy vehicles
Garage floor4 in5–6 in6" recommended; 4" is code minimum
Basement floor3.5 in4 inNot structural — sits on grade
Pole barn / shop floor4 in5–6 in6" for forklifts or heavy equipment
Concrete footing6 in8–12 inDepth below frost line required by code
Foundation wall6 in8–10 inAlways follow engineered plans
Equipment pad (heavy)6 in8 inGenerator, HVAC, compressor pads
⚠ Thicker Is Not Always Better

Going from 4" to 6" on a residential patio adds 50% more concrete cost with no structural benefit for foot traffic. Use the recommended thickness for the application. Overbuild where loads are real (driveways, garage floors, equipment pads); use standard minimums for walkways and patios.

Concrete Mix Types & PSI Guide

Concrete is specified by compressive strength in PSI (pounds per square inch at 28-day cure). Never under-specify PSI on structural elements.

PSI RatingApplicationFreeze-Thaw?Cost PremiumNotes
2,500 PSILight sidewalks, repairsNoBaselineMinimum residential grade — rarely specified today
3,000 PSIPatios, driveways, slabsWith air entrain.+5%Most common residential mix
3,500 PSIGarage floors, retaining wallsYes+10%Good for Zone 4–5 climates
4,000 PSIFoundations, structural slabsYes+15–20%Recommended for cold climates (Zone 5–7)
5,000+ PSICommercial, heavy structuralYes+25–40%Requires engineered mix design

Air Entrainment — Critical for Freeze-Thaw Climates

Air-entrained concrete has billions of microscopic air bubbles that provide relief space for water to expand when it freezes. In Climate Zones 4–7 (anywhere with regular freeze-thaw cycles), always specify air-entrained concrete for exterior slabs, driveways, and walkways. The cost premium is typically $5–$10/cu yd. The alternative is surface damage within 3–5 winters.

Water-to-Cement Ratio — Why Not to Add Water

The strength of concrete is determined primarily by the water-to-cement (w/c) ratio. Adding water at the job site can reduce compressive strength by 30–50% — turning 3,000 PSI mix into 2,000 PSI. If the delivered mix seems stiff, request a plasticizer from your supplier — it improves workability without adding water or reducing strength.

Bags vs Ready-Mix: When to Use Each

Project SizeBest OptionCost ComparisonBags Needed (60 lb)
Under 0.5 cu ydBags (60 or 80 lb)$7–$10/bag — convenient, no minimum~30–35 bags
0.5–1.0 cu ydBags or small mixer$210–$350 bags vs $200–$300 ready-mix + delivery fee~55–60 bags
1–3 cu ydReady-mix (may have short-load fee)$175–$600 ready-mix + $50–$150 short-load fee60–180 bags
3+ cu ydReady-mix truck$390–$600+ delivered — dramatically cheaper than bags180+ bags (impractical)

Ready-Mix Truck Facts

  • Truck capacity: 8–10 cu yd typically (confirm with supplier)
  • Working time: 60–90 minutes from batching — this is your pour window
  • Truck weight: ~66,000 lbs loaded — check driveway and access route weight limits before scheduling delivery
  • Chute reach: Typically 15–18 feet from the truck — plan your pour sequence based on chute reach
  • Short-load fee: $50–$150 for orders under the supplier’s minimum (usually 3–5 cu yd)
✓ The Ready-Mix Decision Rule

If the calculator shows more than 30–35 bags equivalent (roughly 0.5–0.6 cu yd), call for a ready-mix price including the short-load fee. At 1 cu yd+, ready-mix almost always wins on total cost and produces significantly better concrete than hand-mixed bags. At 3+ cu yd, bags become completely impractical — you’d be mixing for hours while the early batches start to cure.

Hidden Costs Most Estimates Miss

1. Subgrade Preparation

Concrete cannot be poured on soft, organic, or poorly compacted soil. Site prep typically includes: excavating 8–12 inches of topsoil, adding 4–6 inches of compacted gravel base, and compacting with a plate compactor. This adds $1–$3/sq ft for a typical slab — $400–$1,200 for a 20×20 ft patio. Use our gravel calculator to estimate the base material separately.

2. Rebar and Reinforcement

Any slab subject to vehicle loads or structural use requires rebar. #4 rebar on 18-inch centers runs $0.60–$1.00/sq ft for the slab area. A 20×20 ft slab needs approximately 280–320 linear feet of rebar. Use our rebar calculator for a precise estimate.

3. Form Lumber

Wood forms (2×4 or 2×6 lumber) are required around the slab perimeter before any pour. For a 20×20 ft slab (80 linear feet of perimeter), form lumber costs $50–$100. Forms can sometimes be reused, but often can’t be removed cleanly after the pour sets.

4. Control Joints

Concrete shrinks as it cures and will crack — control joints give it predetermined places to crack invisibly. Saw-cut control joints should be cut within 6–18 hours of the pour. Saw cutting costs $1–$2 per linear foot. On a 20×20 slab with joints every 10 feet: 40 linear feet = $40–$80 — a service that prevents visible random cracking.

5. Finishing and Sealing

Concrete sealing ($0.25–$0.75/sq ft every 2–5 years) protects the surface from freeze-thaw damage, staining, and wear. Budget $100–$300 for the initial sealing of a residential slab. In climates with road salt, sealing is not optional — it’s the primary protection against surface scaling.

⚠ True All-In Cost for a 20×20 Patio Slab

Concrete material (5.5 cu yd): $715–$963 · Gravel base: $175–$275 · Rebar: $195–$270 · Form lumber: $52–$80 · Screed + tools: $60–$100 · Sealing: $100–$200 · True DIY all-in: $1,297–$1,888. Contractor-poured: $2,800–$4,800. The concrete material is roughly 40–50% of the true project cost.

Common Concrete Mistakes

Ordering the Exact Calculated Amount

Running out mid-pour creates a cold joint — the plane where old and new concrete meet. Cold joints are structurally weak and visible on the surface. Running over is free (extra goes in a wheelbarrow). Running short costs a second truck delivery, a cold joint, and potentially the entire slab. Always order calculated amount + 10%.

Adding Water at the Job Site

When concrete arrives stiff, the instinct is to add water. Every gallon added beyond the design mix raises the water-to-cement ratio and reduces strength — potentially by 30–50%. A 3,000 PSI mix with too much water may test at 2,000 PSI. If the mix seems too stiff, the solution is a plasticizer, not water.

Skipping the Gravel Base

Concrete poured directly on topsoil or clay soil settles unevenly as the soil compresses. The result: cracked, heaved, or sunken slabs within 3–5 years. A 4-inch compacted gravel base is required under every residential slab. The gravel base is structural, not optional.

Not Curing Properly

Concrete gains strength through a chemical hydration process that requires moisture. If the surface dries too quickly (hot weather, wind, low humidity), the top layer cures faster than the interior, causing surface cracking. Cure by covering with plastic sheeting for 7 days, applying a liquid curing compound immediately after finishing, or misting the surface 2–3 times per day for a week.

Pouring in Wrong Weather Conditions

Concrete should only be poured when air temperature is between 40°F and 90°F with no rain forecast for 24 hours. Below 40°F, the hydration process slows or stops. Above 90°F, concrete sets too fast, reducing working time and causing shrinkage cracking. Schedule the pour in early morning in hot weather; use heated water in cold weather.

How We Calculate

Volume (cu ft) = Length × Width × (Thickness in inches ÷ 12)

Cubic Yards = Volume ÷ 27 · Order Amount = Cubic Yards × 1.10

This is the industry-standard formula used by contractors, suppliers, and the ACI. Dividing by 27 converts cubic feet to cubic yards (3 ft × 3 ft × 3 ft = 27 cu ft = 1 cu yd). The 10% waste factor accounts for subgrade variation, form flex, and spillage.

One 60 lb bag yields approximately 0.45 cubic feet of mixed concrete. One 80 lb bag yields approximately 0.60 cubic feet. The bag count shown is the 60 lb bag equivalent — shown to help decide whether bags or ready-mix makes sense, not as a recommendation to use bags on larger projects.

Thickness recommendations are per ACI 318 (Building Code Requirements for Structural Concrete) and IRC (International Residential Code). PSI specifications follow ACI recommendations for residential construction. Ready-mix pricing ranges are based on 2026 supplier pricing across 8 US markets, cross-referenced with RSMeans concrete unit cost data.

Frequently Asked Questions

How many cubic yards of concrete do I need?+
Use the formula: Length × Width × (Thickness in inches ÷ 12) ÷ 27 = cubic yards, then add 10%. For a 20×20 ft slab at 4 inches: 20 × 20 × (4÷12) ÷ 27 = 4.94 cu yd + 10% = 5.43 cu yd to order. The calculator above does this automatically with your exact dimensions.
How thick should a concrete slab be?+
4 inches is standard for residential patios, walkways, and non-vehicle areas per IRC. 5–6 inches for driveways and garage floors that support vehicles. 8 inches for heavy equipment pads. Footings require 8–12 inches depending on load and local building code. The thickness guide above shows ACI and IRC recommended depths for each application.
How many 60 lb bags of concrete in a cubic yard?+
One 60 lb bag yields approximately 0.45 cubic feet. One cubic yard = 27 cubic feet, requiring approximately 60 bags per cubic yard. One 80 lb bag yields 0.60 cubic feet, requiring about 45 bags per cubic yard. For any project over 0.5–1 cubic yard, ready-mix is significantly cheaper — a yard of ready-mix costs $125–$200 delivered vs $420–$600 in 60 lb bags.
How much does a yard of concrete cost?+
Ready-mix concrete costs $125–$200 per cubic yard for standard 3,000 PSI mix in 2026, depending on region. Higher PSI mixes (4,000 PSI, air-entrained) add $15–$30/cu yd. Delivery adds $10–$20/cu yd. Short-load fees ($50–$150) apply for orders under 3–5 yards at most suppliers. For the full installed cost of a slab, use our concrete slab cost calculator.
What PSI concrete should I use for a driveway?+
Use 3,000–4,000 PSI for residential driveways. In freeze-thaw climates (Zones 4–7), use 4,000 PSI with air entrainment — this dramatically improves resistance to freeze-thaw cracking and road salt damage. In mild climates (Zones 1–3), 3,000 PSI without air entrainment is acceptable. Always ask your ready-mix supplier for their recommended mix for your climate.
What is a cold joint in concrete?+
A cold joint is the plane where two concrete pours meet after the first has begun to set. The new concrete doesn’t bond chemically with the hardened concrete — creating a structural weak plane that can allow water infiltration, cracking, and separation. Cold joints are caused by running out of concrete mid-pour or delays between truck deliveries. They’re why the 10% waste buffer is non-negotiable.
Can I pour concrete directly on dirt?+
No — for any structural slab. Topsoil and clay soil compress and expand with moisture, causing the slab to crack, heave, or sink. The correct base is 4–6 inches of compacted gravel (crushed stone), which provides a stable, well-draining foundation. Concrete poured on unprepared soil will fail within years regardless of PSI or thickness. The gravel base is required by code for structural slabs.
📚 References & Data Sources
  1. ACI 318 — Building Code Requirements for Structural Concrete — The primary US standard for concrete design and construction. Referenced for slab thickness minimums by application, PSI specifications for residential structural elements, and cold joint definitions. Thickness guide table values are per ACI 318 and ACI 332 (residential concrete). American Concrete Institute, current edition.
  2. IRC (International Residential Code) — Section R506: Concrete Floors (On Ground) — Code requirements for residential concrete slabs including minimum 3.5-inch thickness, gravel base requirement, and vapor barrier provisions. Referenced for thickness guide and subgrade preparation guidance. ICC, current edition.
  3. ACI 308 — Guide to External Curing of Concrete — Guidance on concrete curing methods, duration (7-day minimum), and effects of premature drying on compressive strength development. Referenced for the curing section in common mistakes. American Concrete Institute, current edition.
  4. RSMeans Building Construction Cost Data 2026 — Unit cost data for ready-mix concrete by PSI and region, contractor labor rates for concrete placement and finishing, and installed cost per square foot benchmarks. Referenced for all pricing ranges in the examples and cost tables. RSMeans / Gordian, 2026.
  5. HomeAdvisor True Cost Guide 2026 — Consumer-reported pricing data for concrete slab installation including contractor quotes by region. Used to cross-validate RSMeans installed cost ranges and provide regional pricing context. HomeAdvisor / Angi, 2026.
  6. Portland Cement Association (PCA) — Design and Control of Concrete Mixtures — Water-to-cement ratio guidance, air entrainment specifications for freeze-thaw climates by exposure class, and plasticizer/superplasticizer usage guidance. Referenced for the PSI guide, air entrainment section, and water addition warning. PCA, current edition.

Cost estimates reflect 2026 US national average pricing. Ready-mix concrete pricing varies significantly by region, PSI specification, and seasonal demand — always confirm current pricing with your local supplier before ordering. ConstructlyTools does not have a paid relationship with any ready-mix supplier, concrete product brand, or contractor mentioned on this page.

Scroll to Top